Project Detail

Project No: 364

BRIDGE REHABILITATION OF THE STH 20 BRIDGES OVER STUART RD AND UP RR (B51-39, B51-40, B51-43, B51-44) IN THE VILLAGE OF MOUNT PLEASANT

State ID:  2340-03-03
Project Type:
  • Highway System Preservation
Air Qualities Status:EXEMPT

Estimated Costs

Detail Costs2023202420252026Remaining
PE00000
Row00000
Const03,044,600000
Other00000
Total03,044,600000
Source of Funds2023202420252026
Local0000
State0608,90000
Federal NHPP02,435,70000
Total03,044,60000
Last Amended: N/A

Return to Projects Listing