Project No: 249
RESURFACING WITH WIDENING OF SHOULDERS OF SUMMIT AVE (USH 18) FROM STH 83 TO STH 318 AND CULVERT REPAIR (C67-73) 0.13 MILES E OF CTH G IN THE TOWN OF DELAFIELD (5.12 MI)
State ID:
2210-12-00
Project Type:
- Highway System Preservation
Air Qualities Status:EXEMPT
Estimated Costs
Detail Costs | 2023 | 2024 | 2025 | 2026 | Remaining |
---|
PE | 0 | 0 | 0 | 0 | 0 |
Row | 0 | 0 | 0 | 0 | 0 |
Const | 5,130,400 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 |
Total | 5,130,400 | 0 | 0 | 0 | 0 |
Source of Funds | 2023 | 2024 | 2025 | 2026 |
---|
Local | 0 | 0 | 0 | 0 |
State | 992,500 | 0 | 0 | 0 |
Federal COMB | 4,137,900 | 0 | 0 | 0 |
Total | 5,130,400 | 0 | 0 | 0 |
Last Amended: N/A
Notes: Project is to be funded with $302,300 in Federal Highway Administration Highway Safety Improvement Program (HSIP) funds and with $3,835,600 in Federal Highway Administration National Highway Performance Program (NHPP) funds.
Return to Projects Listing