Project Detail

Project No: 177

OPERATING ASSISTANCE FOR WASHINGTON COUNTY COMMUTER EXPRESS BUS SERVICE (SEC 85.20 & 5307)

Project Type:
  • Transit Preservation
Air Qualities Status:EXEMPT

Estimated Costs

Detail Costs2019202020212022Remaining
PE00000
Row00000
Const00000
Other1,453,9001,483,0001,512,6001,542,9000
Total1,453,9001,483,0001,512,6001,542,9000
Source of Funds2019202020212022
Local392500400,400408,400416,600
State479,800489,400499,200509,200
Federal FTA 5307581,600593,200605,000617,100
Total1,453,9001,483,0001,512,6001,542,900
Last Amended: N/A