Transportation

 

Project Detail

Project No: 310

REPLACEMENT OF STH 158 BRIDGES OVER THE CP RR AND UP RR LINES, INCLUDING RECONSTRUCTION OF THE ROADWAY BETWEEN THE BRIDGES, IN THE CITY OF KENOSHA (B-30-2 AND B-30-3)

State ID:  3220-09-00
Project Type:
  • Highway System Preservation
Air Qualities Status:EXEMPT

Estimated Costs

Detail Costs2017201820192020Remaining
PE00000
Row00000
Const008,280,00000
Other00000
Total008,280,00000
Source of Funds2017201820192020
Local0000
State001,656,0000
Federal NHPP006,624,0000
Total008,280,0000
Last Amended: N/A